Construction Features of FRP Pipe Jacking
1. Suitable for soft soil or water-rich soft soil layers;
2. No open excavation required, minimal impact on the ground;
3. Minimal equipment requirements, simple process, short construction period, low cost, and high speed;
4. Suitable for medium-sized pipelines (1.5-2m);
5. Large diameter and extra-long jacking can make correction difficult.
FRP pipe manufacturers can construct underground pipelines across roads, railways, rivers, and surface structures.
6. Pipes can be laid very deep underground.
Technical Keys of FRP Pipe Jacking
1. Jacking Force Issues: Increase relay rings and slurry lubrication.
Relay ring spacing is 20-200m, decreasing with increasing distance to the tool pipe.
Slurry Function: Lubrication and Sinking Reduction. Slurry Material: Bentonite slurry, stable and with minimal water loss.
Injection Hole Configuration: Axial - The tool pipe is perforated for the first 3-4 sections, followed by perforated holes every 2-5 sections. Circumferential: 3-4 grouting holes are evenly spaced around the circumference.
Grouting principles: Press first, then push, grouting as you push, and replenishing grouting promptly.
2. Directional control: Computer control, laser guidance, or three-section double-hinged pipe.
3. Frontal soil control: Localized pressurization (flushing silos), slurry balance, and the use of an earth pressure balance pipe jacking machine.